At the Vereda Guayaquil mining project, we closed the month with significant progress in civil works and adaptations at both projects.

In Guayaquil, the following facilities have been completed:

  • Car parks
  • Access platforms
  • Entrance security checkpoint
  • Pending access roads
  • New rainwater pipes

The following works have been completed in the processing plant:

  • Fixing the concrete of warehouse number 2.
  • We are continuing to erect the structure that will support the roof.
  • Installation of the jaw crusher and conveyor belts.

This completes the entire network of crushing and grinding equipment, we still need the final electrical installation.

We are still finishing the construction of the power substation and we are planning to finish the wiring between the towers by the 9th of July.

At present, the loading cableway has been stabilized and is already working at full capacity, although some details are missing in the vibration systems, which are being adjusted day by day until the perfect coupling is achieved.

The laboratory already has the latest precision balance installed and the atomic absorption spectrometer.

This month we received the visit of a group of investors, we leave you the video summary of Guillermo.